Road Closures Ahead in Putney and Roehampton


Diversions and delays in the local area due to road works

putney road closures
Street Parties:
- Langside Avenue SW15
- 17th June O/S 17 to O/S 28
- Gladwyn Road - 23rd June J/W Bendemeer Road to J/W Lower Richmond Road

Clarence Lane, Roehampton

28 May — 15 July

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: WORKING ON BEHALF OF THAMES WATER: SURFACE LOCATION: FW/CW

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU823H553/MHA632/Z004

Clarence Lane, Roehampton

28 May — 15 July

Delays unlikely Some carriageway incursion

Works description: WORKING ON BEHALF OF THAMES WATER: SURFACE LOCATION: FW/CW

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU823H553/MHA632/Z004

A3209 Putney Bridge Road,

04 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: NEW GAS CONNECTION

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB020S000000000478

Fawe Park Road, Putney,

04 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: New Gas Connections

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB020S000000000479

A3209 Putney Bridge Road

04 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: NEW GAS CONNECTION

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB020S000000000478

Gwendolen Avenue, Putney

11 June — 26 June

Delays possible Traffic control (multi-way signals)

Works location: Unknown

Works description: LAY 5M OF 180MM PE, ABANDON 5M OF 8" CI, MAKE 2 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT

Responsibility for works: SOUTHERN GAS NETWORKS PLC

Current status: Advanced planning

Works reference: XW053W114995725-02175

Hazlewell Road, Putney

11 June — 11 September

Delays unlikely Traffic control (give & take)

Works location: Unknown

Works description: LAY 600M OF 180MM PE, 50M OF 63MM PE, ABANDON 600M OF 8" CI, 50M OF 2" CI, TRANSFER 77 SERVICES, MAKE 21 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT

Responsibility for works: SOUTHERN GAS NETWORKS PLC

Current status: Advanced planning

Works reference: XW053W115001687-02281

Holroyd Road, Putney

11 June — 17 July

Delays unlikely Traffic control (give & take)

Works location: Unknown

Works description: LAY 215M OF 125MM PE, ABANDON 215M OF 6" CI, TRANSFER 34 SERVICES, MAKE 2 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT

Responsibility for works: SOUTHERN GAS NETWORKS PLC

Current status: Advanced planning

Works reference: XW053W115030140-02407

A205 Upper Richmond Road, Putney

12 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: GAS DISCONNECTION TO 72 WEST HILL- EXCAVATE IN NEARSIDE FOOTWAY MAINTAINING 1M FOR PEDS

Responsibility for works: SGN

Current status: Planned work about to start

Works reference: XW047W115296187-05667

Chartfield Avenue, Putney

12 June — 15 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: OSV Locate

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU302000031048710-001

Roedean Crescent, Roehampton

12 June — 16 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: DISCONNECT 1X 2" STEEL SERVICE 1M FROM MAIN IN FOOTWAY

Responsibility for works: Cadent

Current status: Planned work about to start

Works reference: AZ0071000720022

Balmuir Gardens, Putney

13 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Service Pipe Repair

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU302000031085956-001

Carlton Drive, Putney

13 June — 27 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: UKPN Infrastructure Works/ New Connection

Responsibility for works: GAS TRANSPORTATION CO LTD

Current status: Planned work about to start

Works reference: ZP011P-00071921/R4

Wadham Road, Putney

13 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Service Pipe Reconnect Footway in Footway. Our intention is to completethe Permanent Reinstatement in the same phase

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU302000031075611-001

Roehampton High Street, Roehampton

14 June — 17 June

Delays likely Road closure

Works location: Unknown

Works description: Resurfacing of the carriageway

Responsibility for works: Transport for London

Current status: Planned work about to start

Works reference: YG417383746

Chartfield Avenue, Putney

14 June — 15 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Crane Operation

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB222S000000000930

Landford Road, Putney

14 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Replace 1 jointbox frame and cover(s) (915mm x 445mm) in Footway

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500264103400

Malbrook Road, Putney

15 June — 20 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: CUSTOMER SIDE LEAKAGE SUPPLY PIPE REPLACEMEN

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU274002251YNSW--000001

Norroy Road, Putney

14 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: REMEDIAL REINSTATEMENT IN THE FOOTWAY

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU275OSV-182439-01

Fawe Park Road, Putney

16 June — 17 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: REMEDIAL REINSTATEMENT IN FOOTWAY

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU275OSV-184197-01

Oxford Road, Putney

16 June — 18 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Remedial works to correct defect, redo fillet

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500261782900

 


Roehampton High Street SW15 will be closed at the junction with Roehampton Lane for TFL resurfacing works commencing 14/06/2018 to 16/06/2018 (night works only). Contact: TFL 0343 222 1234.

Rocks Lane (the bridge by Barnes Station) - will be subject to temporary 2-way traffic signals from 26 February to 10 July. Essential as Bridge will become too weak to take high level of traffic over it if nothing is done. London Buses will continue on their normal routes. The work on Rocks Lane railway bridge will see the use of temporary two way traffic signals which will be controlled manually between the hours of 7am and 7pm to prevent the traffic building up.

Water Leaks and Gas Escapes

Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks

WATER: 0800 714614
GAS: 0800 111999

All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.

For further information please contact the Engineer in the first instance or e-mail streetworks@wandsworth.gov.uk.

June 15, 2018