Forthcoming significant roadworks in the W4 area

The following roadworks are likely to cause some delays in the Chiswick area
        Dates Confirmed for Start of First Phase of Works on Cycleway 9
      Lane closures by Kew Bridge predicted to have major impact on traffic around Chiswick
         A315,A205 Kew Bridge Road, Brentford
        13 January — 07 February
  Delays likely - Lane closure
  Works description : Cycleway 9 - kerb realignment. TM drawings CS9-TM-0021-3, CS9-TM-0022-2. Collaborative working with section 50 licence YG104L-MAIN-00008587/UL2 (Argon Utilities)
  Responsibility for works: Transport for London
  Current status: Advanced planning
  Works reference:  YG65200000149 
  
  A315 Chiswick High Road, Chiswick
  07 February — 10 February 
  Delays likely - Contra-flow 
  Works description : W.R.P - Installation of 3 Bay Non Ad Bus Shelter, Centre of Path, for and on behalf of Transport for London. Shelter ref 0118/0332 2882578 
  Responsibility for works: LONDON TRANSPORT 
  Current status: Planned work about to start 
  Works reference:  RK00100045564 
 A315,A205 Kew Bridge Road, Brentford
      03 February — 10 February 
      Delays likely - Traffic control (multi-way signals) 
      Works description : Build 1 concrete chamber 1220mm x 680mm x 1665mm deep in Carriageway,Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 6 existing jointbox(s) or cabinet base(s),Install 15m of 2 poly ducts in Carriageway,Install 30m of 2 poly ducts in Footway Responsibility for works: Openreach 
      Current status: Planned work about to start 
      Works reference:  BC006TI001LC500289765106 
 Grove Park Terrace, Chiswick
      04 February — 05 February 
      Delays likely - Road closure 
      Works description : Defect remedial reinstatement in the carriageway 
      Responsibility for works: THAMES WATER 
      Current status: Planned work about to start 
      Works reference:  MU301000031169125-001
        
        A316 Dorchester Grove, Chiswick
        03 February — 05 February 
        Delays likely - Traffic control (priority working)
        Works description : Service Pipe Repair <33mm Fway in Footway. Our intention is tocomplete the Permanent Reinstatement in the same phase 
        Responsibility for works: THAMES WATER 
        Current status: Planned work about to start 
      Works reference:  MU301000031414348-001 
A205 Chiswick High Road (north Circular Road), Chiswick
          27 January — 07 February
          Delays likely - Lane closure
          Works description: WBS SC.2769.249.001 Install new vehicle crossover to development Footway only.Bus lane closed for pedestrian walkway
          Responsibility for works: Transport for London
          Current status: Planned work about to start
          Works reference: YG429427306
A315,A205 Kew Bridge Road, Brentford
          27 January — 07 February
          Delays likely - Lane closure
          Works description: CS9 - realignment of northern kerbline TM Ref CS9-TM-0018-1 / 0019-1
          Responsibility for works: Transport for London
          Current status: Advanced planning
          Works reference: YG65200000105
A315,A205 Kew Bridge Road, Brentford
          27 January — 07 February
          Delays likely - Traffic control (multi-way signals)
          Works description: Build 1 concrete chamber 1220mm x 680mm x 1665mm deep in Carriageway,Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 6 existing jointbox(s) or cabinet base(s),Install 15m of 2 poly ducts in Carriageway,Install 30m of 2 poly ducts in Footway
          Responsibility for works: Openreach
          Current status: Planned work about to start
          Works reference: BC006TI001LC500289765103
A315,A205 Kew Bridge Road, Brentford
          27 January — 07 February
          Delays likely - Lane closure
          Works description: FINAL CONNECTION TO NEW WATER MAIN TO BE LAID IN TO NEW DEVELOPMENT
          Responsibility for works: THAMES WATER
          Current status: Planned work about to start
          Works reference: MU30700080184178M002
A315,A205 Kew Bridge Road, Brentford
          27 January — 07 February
          Delays likely - Lane closure
          Works description: Build 4 concrete chamber 915mm x 445mm x 965mm deep in Footway,Demolish 4 existing jointbox(s) or cabinet base(s),Reinstate 12.08m3 following excavation in Footway,Reinstate 17.50m2 following excavation in Footway,Reposition 25m of 1 way poly duct,Reposition 25m of up to 6 way poly ducts
          Responsibility for works: Openreach
          Current status: Planned work about to start
          Works reference: BC006TI001LC500289765102
Source: www.roadworks.org
Like Reading Articles Like This? Help Us Produce More This site remains committed to providing local community news and public interest journalism. Articles such as the one above are integral to what we do. We aim to feature as much as possible on local societies, charities based in the area, fundraising efforts by residents, community-based initiatives and even helping people find missing pets. We've always done that and won't be changing, in fact we'd like to do more. However, the readership that these stories generates is often below that needed to cover the cost of producing them. Our financial resources are limited and the local media environment is intensely competitive so there is a constraint on what we can do. We are therefore asking our readers to consider offering financial support to these efforts. Any money given will help support community and public interest news and the expansion of our coverage in this area. A suggested monthly payment is £8 but we would be grateful for any amount for instance if you think this site offers the equivalent value of a subscription to a daily printed newspaper you may wish to consider £20 per month. If neither of these amounts is suitable for you then contact info@neighbournet.com and we can set up an alternative. All payments are made through a secure web site. One-off donations are also appreciated. Choose The Amount You Wish To Contribute. If you do support us in this way we'd be interested to hear what kind of articles you would like to see more of on the site – send your suggestions to the editor. For businesses we offer the chance to be a corporate sponsor of community content on the site. For £30 plus VAT per month you will be the designated sponsor of at least one article a month with your logo appearing if supplied. If there is a specific community group or initiative you'd like to support we can make sure your sponsorship is featured on related content for a one off payment of £50 plus VAT. All payments are made through a secure web site.  | 
        