14 July — 28 July |
||
Delays likely Traffic control (two-way signals) |
||
Works location: A205 |
||
Works description: Approx 102m Excavation Dual Hv Circuit - Hv Supply To New Brentford Stadium Development. Ttro Application Also Required For Road Closure On Lionel Road South, Lane Closure At Jnc With South Circular Road And Capital Interchange Way. |
||
Responsibility for works: Gas Transportation Co Ltd |
||
Current status: Advanced planning |
16 July — 17 July |
||
Delays likely Contra-flow |
||
Works location: A406 |
||
Works description: Closure Of One Lane In Both Directions, Maintaining Traffic Flow With A Contraflow System To Facilitate Lifting Of Service Bridge. The Contraflow Will Be On The Eastern Side Of The Main Bridge. |
||
Responsibility for works: Transport For London |
||
Current status: Planned work about to start |
|
||||||||||
14 July — 28 July |
||
Delays likely Traffic control (two-way signals) |
||
Works location: A205 |
||
Works description: Approx 102m Excavation Dual Hv Circuit - Hv Supply To New Brentford Stadium Development. Ttro Application Also Required For Road Closure On Lionel Road South, Lane Closure At Jnc With South Circular Road And Capital Interchange Way. |
||
Responsibility for works: Gas Transportation Co Ltd |
||
Current status: Advanced planning |
04 July — 09 August |
||
Delays likely Road closure |
||
Works location: - |
||
Works description: - |
||
Responsibility for works: National Grid Gas Plc |
||
Current status: Planned work about to start |
|
|
||||||||||
|