Traffic Delays Likely in Chiswick
Forthcoming significant roadworks in the W4 area  
            
      The following roadworks are likely to cause some delays in the Chiswick area: Some may not cause delays but residents may be interested to know of work going on in advance. 
      
        
           Stile Hall Gardens, Chiswick  | 
         
        
           16 March — 23 March   | 
         
        
           Delays likely Road closure   | 
         
        
           Works location: -   | 
         
        
           Works description: -   | 
         
        
           Responsibility for works: Hounslow London Borough Council   | 
         
        
           Current status: Advanced planning   | 
         
             
      
        
           A315 Chiswick High Road  | 
         
        
           17 March — 18 March   | 
           | 
           | 
         
        
           Delays likely Lane closure   | 
           | 
         
        
           Works location: A315   | 
           | 
           | 
         
        
           Works description: 25/263 Tel0071489 - Access Tfl Traffic Signal Mast Arm, Suspect Fault On Rag Head. Both Led Greens On Mast Arm Need Replacing. 22:00-05:00. W/B Lane 2. No Noisy Works   | 
           | 
           | 
         
        
           Responsibility for works: Transport For London   | 
           | 
           | 
         
        
           Current status: Planned work about to start   | 
           | 
           | 
         
             
      
        
          
              
                 A315 King Street  | 
               
              
                 15 March — 30 March   | 
                
                
               
              
                 Delays likely Lane closure   | 
                
               
              
                 Works location: A315   | 
                
                
               
              
                 Works description: Dig Down And Locate The Water Main And Check On The Condition And Take A Measurement.   | 
                
                
               
              
                 Responsibility for works: Thames Tideway Tunnel Ltd   | 
                
                
               
              
                 Current status: Planned work about to start   | 
                
                
               
            | 
         
        
          
         
        
          
              
                 A316 Great Chertsey Road, Chiswick  | 
               
              
                 15 March — 16 March   | 
                
                
               
              
                 Delays likely Lane closure   | 
                
               
              
                 Works location: A316   | 
                
                
               
              
                 Works description: Cpp - Cyclic, Maintenance, Annual Works, Collaborative Working. (Lane 2 Of 2 Closed Changing To Lane 1 Of 2 Closed)   | 
                
                
               
              
                 Responsibility for works: Transport For London   | 
                
                
               
              
                 Current status: Planned work about to start   | 
                
                
               
            | 
         
        
          
         
        
          
         
             
            
      
        
          
         
        
          
              
                A406 Gunnersbury Avenue (North Circular Road)  | 
               
              
                11 January — 28 March Lane closure   | 
                
                
               
              
                Delays likely due to Streetworks  
              Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 24/7 Fw 2100 - 0530 Cw at A406   | 
                
                
               
              
                Responsibility: Transport For London   | 
                
                
               
              
                EToN status: Planned work about to start   | 
                
                
               
              
                
                
                
               
            | 
         
        
          
         
        
          
              
                A406 Gunnersbury Avenue  | 
               
              
                11 January — 28 March Lane closure   | 
                
                
               
              
                Delays likely due to Streetworks  
              Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 24/7 Fw 2100 - 0530 Cw. No Works To Take Place Night Of 05/02 - 06/02/16. at A406   | 
                
                
               
              
                Responsibility: Transport For London   | 
                
                
               
              
                EToN status: Planned work about to start   | 
                
                
               
              
                
                
                
               
            | 
         
        
          
         
        
          
              
                B4491/A4000 Gunnersbury Lane  | 
               
              
                11 January — 28 March Lane closure   | 
                
                
               
              
                Delays likely due to Streetworks  
              Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 2000 - 0500(F/W) 2200 - 0500 (C/W) at B4491/A4000   | 
                
                
               
              
                Responsibility: Transport For London   | 
                
                
               
              
                EToN status: Planned work about to start   | 
                
                
               
              
                
                
                
               
            | 
         
        
          
         
        
          
              
                B4491 Popes Lane  | 
               
              
                11 January — 28 March Lane closure   | 
                
                
               
              
                Delays likely due to Streetworks  
              Ti Modernisation Scheme/ Pedestrian Crossing Lane 1 Switch To Lane 2 Closure And Back To Back Lane 2'S Around Ped Islands. Works To Finish 16/12/15 And Continue 04/01/16 2000 - 0500 (F/W) 2200 - 0500 (C/W) Tman N1501164-001-W001 at B4491   | 
                
                
               
              
                Responsibility: Transport For London   | 
                
                
               
              
                EToN status: Planned work about to start   | 
                
                
               
              
                
                
                
               
            | 
         
        
          
         
             
        
      Source: www.roadworks.org  
            
         
      
        |